AEP Texas representatives plan to invest about $63 million to rebuild an 54-mile 138-kilovolt electric transmission line in Eagle Pass and Del Rio. Plans involve replacing deteriorating wooden poles from the 1950s with modern steel poles. The existing transmission line has experienced several outages since 2015 and these improvements enhance the line's operational performance.
April 2022 - Right-of-way agents plan to begin communications to landowners about preliminary field activities such as soil boring and environmental surveys late spring.
Typical Structure Height: 75 -105 feet
Typical Distance between Structures: 600 - 800 feet
Typical Right-of-Way width: 100 feet
*Exact structure, height and right-of-way may vary
AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.