Hamilton Road - Del RioTransmission Line Project


[EspaƱol]

AEP Texas representatives plan to invest about $19 million to rebuild an 8-mile 138-kilovolt electric transmission line in Del Rio. Plans involve replacing deteriorating wooden poles with modern steel poles and minor upgrades at four area substations.

Project Updates

Right-of-way agents plan to begin communications to landowners about acquisition summer 2022. Construction activities are expected to start fall 2022.

Timeline

Project Timeline

Structures

Structure

Typical Structure Height: Approximately 85-100 feet

*Exact structure, height and right-of-way requirements may vary

Resources

Project Fact Sheet Access Roads Field Activities

AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.

www.AEPTexas.com