Pleasanton - Three RiversTransmission Line Project


AEP Texas representatives plan to invest about $63 million to rebuild an 29-mile 138-kilovolt electric transmission line in Eagle Pass. Plans involve replacing deteriorating wooden poles from the 1950s with modern steel poles. The existing transmission line has experienced several outages since 2015 and these improvements enhance the line's operational performance.

Project Updates

Right-of-way agents plan to begin communications to landowners about preliminary field activities later this fall.

Timeline

 
Project Timeline
 

Structures

Structure
  • Monopole Delta Braced Post Tangent
  • Monopole Alternating Braced Post Tangent

*Exact structure, height and right-of-way may vary

Resources

Project Fact Sheet Access Roads Field Activities

AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.