The Open House Webinar was held on September 30th, 2020. Due to COVID-19 restrictions, Entergy will post all materials on this website that would be available for review at an in-person open house.
These are the presentation boards that would be on display at an in-person open house. Explore the different topics of interest and click on the thumbnail to expand the board and download the pdf (high resolution) if desired.
purpose and need
certification process
right-of-way acquisition
right-of-way clearing
typical structure
138 kV tangent structure
138 kV dead-end structure
138 kV angle structure
typical substation
agencies contacted
evaluation criteria
constraints
aerial figures index 1
aerial figures index 2
aerial figures index 3
The graphics below are demonstrative examples of a typical construction scenario and configuration. Scenarios may vary by line segment.